How long does a Commercial / Multi Family Project permit take in Braeside, Calgary?
Median days · Applied → Issued
26 days
Sample: 14 permits, last 24 months
Median days · Issued → Completed
35 days
From permit issuance to completion
City-wide median
42 days
Braeside is 16 days faster
Recent examples in Braeside
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11158 | Improvement | Belfor Restoration Services | 2026-06-17 | 2026-07-13 | 26 | $69K |
| BP2026-12498 | Unspecified | — | 2026-07-06 | 2026-07-08 | 2 | $6K |
| BP2026-04779 | Improvement | Dena Development | 2026-03-26 | 2026-04-22 | 27 | $14K |
| BP2026-04267 | Improvement | Abris Construction Calgary | 2026-03-19 | 2026-04-10 | 22 | $90K |
| BP2026-01853 | Improvement | Choice Specialty Services | 2026-02-06 | 2026-03-03 | 25 | $25K |