How long does a Single Construction Permit permit take in Bowness, Calgary?
Median days · Applied → Issued
35 days
Sample: 73 permits, last 24 months
Median days · Issued → Completed
311 days
From permit issuance to completion
City-wide median
18 days
Bowness is 17 days slower
Recent examples in Bowness
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11114 | New | Southern Alberta | 2026-06-17 | 2026-09-08 | 83 | $405K |
| BP2026-10394 | New | Eon Plumbing and Heating | 2026-06-08 | 2026-07-30 | 52 | $463K |
| BP2026-10272 | New | Alberta Luxury Builds | 2026-06-05 | 2026-07-30 | 55 | $376K |
| BP2026-10266 | New | Alberta Luxury Builds | 2026-06-05 | 2026-07-30 | 55 | $346K |
| BP2026-11024 | New | Stanley Regan Construction | 2026-06-16 | 2026-07-21 | 35 | $808K |