How long does a Commercial / Multi Family Project permit take in Bowness, Calgary?

Rolling 24 months · Sample: 139
Median days · Applied → Issued
111 days
Sample: 139 permits, last 24 months
Median days · Issued → Completed
248 days
From permit issuance to completion
City-wide median
42 days
Bowness is 69 days slower

Recent examples in Bowness

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16957UnspecifiedBanff Fire and Safety2026-09-032026-09-085$7K
BP2026-08205New2026-05-122026-09-08119$43K
BP2025-24157NewSunstar Homes2025-12-232026-08-31251$1.1M
BP2026-05547NewQ2026-04-082026-08-18132$249K
BP2026-01743NewSuper Star Luxury Homes2026-02-052026-08-18194$384K