How long does a Commercial / Multi Family Project permit take in Bowness, Calgary?
Median days · Applied → Issued
111 days
Sample: 139 permits, last 24 months
Median days · Issued → Completed
248 days
From permit issuance to completion
City-wide median
42 days
Bowness is 69 days slower
Recent examples in Bowness
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16957 | Unspecified | Banff Fire and Safety | 2026-09-03 | 2026-09-08 | 5 | $7K |
| BP2026-08205 | New | — | 2026-05-12 | 2026-09-08 | 119 | $43K |
| BP2025-24157 | New | Sunstar Homes | 2025-12-23 | 2026-08-31 | 251 | $1.1M |
| BP2026-05547 | New | Q | 2026-04-08 | 2026-08-18 | 132 | $249K |
| BP2026-01743 | New | Super Star Luxury Homes | 2026-02-05 | 2026-08-18 | 194 | $384K |