How long does a Single Construction Permit permit take in Belvedere, Calgary?
Median days · Applied → Issued
18 days
Sample: 108 permits, last 24 months
Median days · Issued → Completed
185 days
From permit issuance to completion
City-wide median
18 days
Same as Belvedere
Recent examples in Belvedere
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-08364 | New | Crystal Creek Homes | 2026-05-13 | 2026-06-13 | 31 | $279K |
| BP2026-07411 | New | Crystal Creek Homes | 2026-05-02 | 2026-06-03 | 32 | $274K |
| BP2026-06642 | New | Crystal Creek Homes | 2026-04-23 | 2026-05-13 | 20 | $274K |
| BP2026-05358 | New | Crystal Creek Homes | 2026-04-07 | 2026-05-08 | 31 | $228K |
| BP2026-02675 | New | Crystal Creek Homes | 2026-02-23 | 2026-03-04 | 9 | $261K |