How long does a Commercial / Multi Family Project permit take in Belvedere, Calgary?
Median days · Applied → Issued
47 days
Sample: 99 permits, last 24 months
Median days · Issued → Completed
220 days
From permit issuance to completion
City-wide median
42 days
Belvedere is 5 days slower
Recent examples in Belvedere
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15639 | Improvement | Primeridge Construction | 2026-08-18 | 2026-09-10 | 23 | $15K |
| BP2025-07277 | New | — | 2025-04-23 | 2026-09-08 | 503 | $3.8M |
| BP2026-14434 | New | Mountain Pacific Homes | 2026-07-30 | 2026-09-06 | 38 | $1.3M |
| BP2026-12305 | Improvement | Neutech Electrical and Mechanical Services | 2026-07-02 | 2026-09-01 | 61 | $150K |
| BP2026-08660 | Improvement | Grand Scale Construction | 2026-05-18 | 2026-08-20 | 94 | $36K |