How long does a Demolition permit take in Beltline, Calgary?

Rolling 24 months · Sample: 20
Median days · Applied → Issued
12 days
Sample: 20 permits, last 24 months
Median days · Issued → Completed
87 days
From permit issuance to completion
City-wide median
4 days
Beltline is 8 days slower

Recent examples in Beltline

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-05278DemolitionPrattco Excavating2026-04-062026-04-082$0
BP2025-22910DemolitionPriestly Demolition2025-11-282026-01-2154$0
BP2026-00128DemolitionSbi Strategic2026-01-052026-01-083$0
BP2025-22291DemolitionPriestly Demolition2025-11-182025-12-0113$0
BP2025-18138DemolitionPriestly Demolition2025-09-162025-10-0216$0