How long does a Demolition permit take in Beltline, Calgary?
Median days · Applied → Issued
12 days
Sample: 20 permits, last 24 months
Median days · Issued → Completed
87 days
From permit issuance to completion
City-wide median
4 days
Beltline is 8 days slower
Recent examples in Beltline
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-05278 | Demolition | Prattco Excavating | 2026-04-06 | 2026-04-08 | 2 | $0 |
| BP2025-22910 | Demolition | Priestly Demolition | 2025-11-28 | 2026-01-21 | 54 | $0 |
| BP2026-00128 | Demolition | Sbi Strategic | 2026-01-05 | 2026-01-08 | 3 | $0 |
| BP2025-22291 | Demolition | Priestly Demolition | 2025-11-18 | 2025-12-01 | 13 | $0 |
| BP2025-18138 | Demolition | Priestly Demolition | 2025-09-16 | 2025-10-02 | 16 | $0 |