How long does a Commercial / Multi Family Project permit take in Beltline, Calgary?
Median days · Applied → Issued
29 days
Sample: 394 permits, last 24 months
Median days · Issued → Completed
85 days
From permit issuance to completion
City-wide median
42 days
Beltline is 13 days faster
Recent examples in Beltline
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15947 | Improvement | — | 2026-08-21 | 2026-09-11 | 21 | $10K |
| BP2026-15293 | Improvement | W D Construction and Millwork | 2026-08-12 | 2026-09-11 | 30 | $500K |
| BP2026-15714 | Improvement | — | 2026-08-18 | 2026-09-10 | 23 | $380K |
| BP2026-13544 | Improvement | — | 2026-07-20 | 2026-09-08 | 50 | $100K |
| BP2026-10282 | Improvement | Choice Specialty Services | 2026-06-06 | 2026-09-04 | 90 | $475K |