How long does a Commercial / Multi Family Project permit take in Beltline, Calgary?

Rolling 24 months · Sample: 394
Median days · Applied → Issued
29 days
Sample: 394 permits, last 24 months
Median days · Issued → Completed
85 days
From permit issuance to completion
City-wide median
42 days
Beltline is 13 days faster

Recent examples in Beltline

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15947Improvement2026-08-212026-09-1121$10K
BP2026-15293ImprovementW D Construction and Millwork2026-08-122026-09-1130$500K
BP2026-15714Improvement2026-08-182026-09-1023$380K
BP2026-13544Improvement2026-07-202026-09-0850$100K
BP2026-10282ImprovementChoice Specialty Services2026-06-062026-09-0490$475K