How long does a Single Construction Permit permit take in Aspen Woods, Calgary?
Median days · Applied → Issued
27 days
Sample: 59 permits, last 24 months
Median days · Issued → Completed
273 days
From permit issuance to completion
City-wide median
18 days
Aspen Woods is 9 days slower
Recent examples in Aspen Woods
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15040 | New | Crystal Creek Homes | 2026-08-10 | 2026-09-11 | 32 | $369K |
| BP2026-12499 | New | Homes by Us | 2026-07-06 | 2026-08-04 | 29 | $459K |
| BP2026-12383 | New | Homes by Us | 2026-07-03 | 2026-07-20 | 17 | $564K |
| BP2026-07466 | New | Crystal Creek Homes | 2026-05-04 | 2026-06-15 | 42 | $572K |
| BP2026-07902 | New | Homes by Us | 2026-05-08 | 2026-06-10 | 33 | $525K |