How long does a Commercial / Multi Family Project permit take in Aspen Woods, Calgary?
Median days · Applied → Issued
66 days
Sample: 21 permits, last 24 months
Median days · Issued → Completed
148 days
From permit issuance to completion
City-wide median
42 days
Aspen Woods is 24 days slower
Recent examples in Aspen Woods
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-09156 | Improvement | — | 2026-05-25 | 2026-06-25 | 31 | $180K |
| BP2026-07579 | Improvement | — | 2026-05-05 | 2026-05-27 | 22 | $462K |
| BP2026-01414 | Improvement | — | 2026-01-30 | 2026-02-24 | 25 | $20K |
| BP2025-24305 | New | Rarebuilt Homes | 2025-12-31 | 2026-01-28 | 28 | $2.1M |
| BP2025-15064 | New | Rarebuilt Homes | 2025-08-04 | 2026-01-26 | 175 | $2.5M |