How long does a Single Construction Permit permit take in Alpine Park, Calgary?
Median days · Applied → Issued
21 days
Sample: 465 permits, last 24 months
Median days · Issued → Completed
195 days
From permit issuance to completion
City-wide median
18 days
Alpine Park is 3 days slower
Recent examples in Alpine Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15168 | New | Homes by Avi | 2026-08-11 | 2026-09-10 | 30 | $352K |
| BP2026-14961 | New | Sterling Homes | 2026-08-07 | 2026-09-08 | 32 | $359K |
| BP2026-14819 | New | Calbridge Homes | 2026-08-06 | 2026-09-03 | 28 | $287K |
| BP2026-10479 | New | Homes by Dream | 2026-06-09 | 2026-09-02 | 85 | $374K |
| BP2026-14643 | New | Sterling Homes | 2026-08-04 | 2026-08-31 | 27 | $364K |