How long does a Commercial / Multi Family Project permit take in Alpine Park, Calgary?
Median days · Applied → Issued
45 days
Sample: 62 permits, last 24 months
Median days · Issued → Completed
243 days
From permit issuance to completion
City-wide median
42 days
Alpine Park is 3 days slower
Recent examples in Alpine Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12324 | Improvement | — | 2026-07-02 | 2026-09-10 | 70 | $700K |
| BP2026-07347 | New | Nuvista Homes | 2026-05-01 | 2026-09-03 | 125 | $884K |
| BP2026-12716 | Improvement | — | 2026-07-08 | 2026-08-30 | 53 | $525K |
| BP2026-12776 | Improvement | — | 2026-07-09 | 2026-08-18 | 40 | $250K |
| BP2026-13303 | New | — | 2026-07-16 | 2026-08-11 | 26 | $1.1M |