How long does a Demolition permit take in Acadia, Calgary?
Median days · Applied → Issued
6 days
Sample: 12 permits, last 24 months
Median days · Issued → Completed
55 days
From permit issuance to completion
City-wide median
4 days
Acadia is 2 days slower
Recent examples in Acadia
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16794 | Demolition | Cloverhill Construction | 2026-09-02 | 2026-09-09 | 7 | $0 |
| BP2026-15048 | Demolition | Luminous Star Abatement | 2026-08-10 | 2026-08-12 | 2 | $0 |
| BP2026-15051 | Demolition | Luminous Star Abatement | 2026-08-10 | 2026-08-12 | 2 | $0 |
| BP2026-14971 | Demolition | Luminous Star Abatement | 2026-08-07 | 2026-08-11 | 4 | $0 |
| BP2026-07452 | Demolition | Western One Excavation | 2026-05-04 | 2026-05-13 | 9 | $0 |