How long does a Commercial / Multi Family Project permit take in Acadia, Calgary?
Median days · Applied → Issued
36 days
Sample: 43 permits, last 24 months
Median days · Issued → Completed
63 days
From permit issuance to completion
City-wide median
42 days
Acadia is 6 days faster
Recent examples in Acadia
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12325 | Unspecified | — | 2026-07-02 | 2026-08-07 | 36 | $28K |
| BP2026-13155 | Improvement | — | 2026-07-14 | 2026-08-07 | 24 | $0 |
| BP2026-10973 | Improvement | — | 2026-06-15 | 2026-07-23 | 38 | $80K |
| BP2026-11720 | Improvement | — | 2026-06-25 | 2026-07-21 | 26 | $850K |
| BP2026-10320 | New | Crescent Homes | 2026-06-08 | 2026-07-02 | 24 | $800K |