Commercial / Multi Family Project at #13 19 AERO DR NE

Completed Permit #BP2025-21722 · Calgary International Airport, Calgary

Details

Class
Improvement
Address
#13 19 AERO DR NE
Community
Calgary International Airport
Contractor
Swift Builders
Est. project cost
$250K
Applied
2025-11-07
Issued
2026-01-29
Completed
2026-04-15

Description

Interior Renovation

Inspection timeline

  1. Progress · Building Deficiencies
    Acceptable with Conditions · 2026-04-14
  2. Final · Building Deficiencies
    Acceptable with Conditions · 2026-04-15