Commercial / Multi Family Project at ARBOUR LAKE CO NW

Completed Permit #BP2025-10246 · Arbour Lake, Calgary

Details

Class
New
Address
ARBOUR LAKE CO NW
Community
Arbour Lake
Contractor
Cantiro Homes Arbour Lake
Est. project cost
$1.6M
Housing units
12
Applied
2025-05-29
Issued
2025-08-19
Completed
2026-07-16

Description

Building 7 - 12 unit townhouse

Inspection timeline

  1. Progress · Building Deficiencies
    Acceptable with Conditions · 2026-07-09
  2. Final · Building Deficiencies
    Acceptable with Conditions · 2026-07-16
  3. Occupancy · Building Deficiencies
    Pass · 2026-07-16