Residential Improvement Project at CREEKVIEW MR SW

Completed Permit #BP2025-09418 · Pine Creek, Calgary

Details

Class
New
Address
CREEKVIEW MR SW
Community
Pine Creek
Est. project cost
$84K
Housing units
1
Applied
2025-05-20
Issued
2025-05-30
Completed
2025-11-21

Description

Secondary Suite

Inspection timeline

  1. Final · Building Deficiencies
    Fail · 2025-10-28
  2. Final · Building Deficiencies
    Fail · 2025-10-31
  3. Final · Building Deficiencies
    Fail · 2025-11-07
  4. Final · Building Deficiencies
    Fail · 2025-11-13
  5. Final · Building Deficiencies
    Fail · 2025-11-17
  6. Final · Building Deficiencies
    Acceptable with Conditions · 2025-11-21