Residential Improvement Project at ROYAL BIRCH HL NW

Completed Permit #BP2024-21130 · Royal Oak, Calgary

Details

Class
Improvement
Address
ROYAL BIRCH HL NW
Community
Royal Oak
Contractor
Continent Constructions
Est. project cost
$57K
Housing units
1
Applied
2024-10-04
Issued
2024-12-03
Completed
2025-03-18

Description

Secondary Suite

Inspection timeline

  1. Framing · Building Deficiencies
    Fail · 2025-02-18
  2. Final · Building Deficiencies