Commercial / Multi Family Project at NA'A CR SW

Completed Permit #BP2024-09284 · Medicine Hill, Calgary

Details

Class
New
Address
NA'A CR SW
Community
Medicine Hill
Contractor
Kalamoir Construction
Est. project cost
$1.6M
Housing units
12
Applied
2024-05-15
Issued
2024-10-09
Completed
2025-03-18

Description

12-unit stacked townhome (Block J Building 2)

Inspection timeline

  1. Final · Building Deficiencies
    Acceptable Add Inspection · 2025-02-19
  2. Final · Building Deficiencies