How long does a Commercial / Multi Family Project permit take in Yorkville, Calgary?

Rolling 24 months · Sample: 27
Median days · Applied → Issued
53 days
Sample: 27 permits, last 24 months
Median days · Issued → Completed
168 days
From permit issuance to completion
City-wide median
42 days
Yorkville is 11 days slower

Recent examples in Yorkville

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-11044NewMattamy Homes2026-06-162026-08-0449$880K
BP2026-12150NewMattamy Homes2026-06-302026-08-0435$818K
BP2026-05100New2026-04-012026-06-3090$804K
BP2026-06769NewMattamy Homes2026-04-242026-06-0340$813K
BP2026-05182New2026-04-022026-04-3028$824K