How long does a Commercial / Multi Family Project permit take in Yorkville, Calgary?
Median days · Applied → Issued
53 days
Sample: 27 permits, last 24 months
Median days · Issued → Completed
168 days
From permit issuance to completion
City-wide median
42 days
Yorkville is 11 days slower
Recent examples in Yorkville
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11044 | New | Mattamy Homes | 2026-06-16 | 2026-08-04 | 49 | $880K |
| BP2026-12150 | New | Mattamy Homes | 2026-06-30 | 2026-08-04 | 35 | $818K |
| BP2026-05100 | New | — | 2026-04-01 | 2026-06-30 | 90 | $804K |
| BP2026-06769 | New | Mattamy Homes | 2026-04-24 | 2026-06-03 | 40 | $813K |
| BP2026-05182 | New | — | 2026-04-02 | 2026-04-30 | 28 | $824K |