How long does a Commercial / Multi Family Project permit take in Woodlands, Calgary?
Median days · Applied → Issued
30 days
Sample: 16 permits, last 24 months
Median days · Issued → Completed
95 days
From permit issuance to completion
City-wide median
42 days
Woodlands is 12 days faster
Recent examples in Woodlands
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13538 | Improvement | True North Concrete Cutting and Coring | 2026-07-20 | 2026-09-01 | 43 | $5K |
| BP2026-12539 | Unspecified | — | 2026-07-07 | 2026-07-11 | 4 | $450K |
| BP2026-12597 | Unspecified | Sprouse Fire and Safety | 2026-07-07 | 2026-07-11 | 4 | $12K |
| BP2026-07016 | Improvement | Keat Contracting | 2026-04-28 | 2026-05-19 | 21 | $75K |
| BP2026-05143 | Improvement | — | 2026-04-01 | 2026-04-30 | 29 | $80K |