How long does a Commercial / Multi Family Project permit take in Woodbine, Calgary?
Median days · Applied → Issued
40 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
68 days
From permit issuance to completion
City-wide median
42 days
Woodbine is 2 days faster
Recent examples in Woodbine
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13536 | Improvement | White Knight Construction | 2026-07-20 | 2026-08-06 | 17 | $25K |
| BP2026-06093 | Improvement | — | 2026-04-16 | 2026-06-11 | 56 | $40K |
| BP2026-06629 | Improvement | — | 2026-04-23 | 2026-05-13 | 20 | $200K |
| BP2026-01855 | Improvement | — | 2026-02-06 | 2026-04-28 | 81 | $126K |
| BP2024-20294 | Improvement | — | 2024-09-24 | 2024-10-24 | 30 | $160K |