How long does a Residential Improvement Project permit take in Willow Park, Calgary?
Median days · Applied → Issued
22 days
Sample: 91 permits, last 24 months
Median days · Issued → Completed
108 days
From permit issuance to completion
City-wide median
17 days
Willow Park is 5 days slower
Recent examples in Willow Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11615 | Improvement | — | 2026-06-24 | 2026-09-11 | 79 | $25K |
| BP2026-15214 | Improvement | True North Concrete Cutting and Coring | 2026-08-11 | 2026-08-26 | 15 | $4K |
| BP2026-13123 | Improvement | — | 2026-07-14 | 2026-08-20 | 37 | $2K |
| BP2026-14492 | Improvement | — | 2026-07-31 | 2026-08-19 | 19 | $50K |
| BP2026-13412 | Improvement | Woolrich Group Design and Construction | 2026-07-17 | 2026-08-17 | 31 | $13K |