How long does a Commercial / Multi Family Project permit take in Westwinds, Calgary?
Median days · Applied → Issued
50 days
Sample: 76 permits, last 24 months
Median days · Issued → Completed
105 days
From permit issuance to completion
City-wide median
42 days
Westwinds is 8 days slower
Recent examples in Westwinds
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12036 | Improvement | — | 2026-06-29 | 2026-09-02 | 65 | $0 |
| BP2026-14205 | Improvement | — | 2026-07-28 | 2026-08-31 | 34 | $500K |
| BP2026-11301 | Improvement | Tailored Electrical Services | 2026-06-19 | 2026-08-25 | 67 | $40K |
| BP2026-12824 | Improvement | — | 2026-07-09 | 2026-08-13 | 35 | $35K |
| BP2026-07674 | Improvement | — | 2026-05-06 | 2026-08-12 | 98 | $0 |