How long does a Demolition permit take in Westgate, Calgary?
Median days · Applied → Issued
8 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
196 days
From permit issuance to completion
City-wide median
4 days
Westgate is 4 days slower
Recent examples in Westgate
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-04647 | Demolition | Shemsho Construction | 2026-03-25 | 2026-03-27 | 2 | $0 |
| BP2025-19736 | Demolition | Albert Potter Bob Cat Services | 2025-10-07 | 2025-10-15 | 8 | $0 |
| BP2025-19740 | Demolition | Albert Potter Bob Cat Services | 2025-10-07 | 2025-10-15 | 8 | $0 |
| BP2025-19741 | Demolition | Albert Potter Bob Cat Services | 2025-10-07 | 2025-10-15 | 8 | $0 |
| BP2025-18393 | Demolition | P and G Excavating Trucking | 2025-09-18 | 2025-09-24 | 6 | $0 |