How long does a Commercial / Multi Family Project permit take in West Springs, Calgary?
Median days · Applied → Issued
52 days
Sample: 84 permits, last 24 months
Median days · Issued → Completed
168 days
From permit issuance to completion
City-wide median
42 days
West Springs is 10 days slower
Recent examples in West Springs
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11466 | Improvement | — | 2026-06-22 | 2026-09-10 | 80 | $70K |
| BP2026-13402 | Improvement | — | 2026-07-17 | 2026-08-13 | 27 | $850K |
| BP2026-04450 | New | — | 2026-03-23 | 2026-07-30 | 129 | $11.6M |
| BP2026-08910 | Improvement | — | 2026-05-21 | 2026-07-29 | 69 | $170K |
| BP2026-09201 | Improvement | — | 2026-05-26 | 2026-07-29 | 64 | $332K |