How long does a Single Construction Permit permit take in Walden, Calgary?
Median days · Applied → Issued
18 days
Sample: 82 permits, last 24 months
Median days · Issued → Completed
192 days
From permit issuance to completion
City-wide median
18 days
Same as Walden
Recent examples in Walden
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-07827 | New | Daytona Homes | 2026-05-07 | 2026-06-03 | 27 | $386K |
| BP2026-03633 | New | Daytona Homes | 2026-03-10 | 2026-03-26 | 16 | $303K |
| BP2026-03970 | New | Daytona Homes | 2026-03-16 | 2026-03-26 | 10 | $359K |
| BP2026-01255 | New | Daytona Homes | 2026-01-27 | 2026-02-02 | 6 | $335K |
| BP2026-00956 | New | Daytona Homes | 2026-01-21 | 2026-01-29 | 8 | $330K |