How long does a Single Construction Permit permit take in Walden, Calgary?

Rolling 24 months · Sample: 82
Median days · Applied → Issued
18 days
Sample: 82 permits, last 24 months
Median days · Issued → Completed
192 days
From permit issuance to completion
City-wide median
18 days
Same as Walden

Recent examples in Walden

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-07827NewDaytona Homes2026-05-072026-06-0327$386K
BP2026-03633NewDaytona Homes2026-03-102026-03-2616$303K
BP2026-03970NewDaytona Homes2026-03-162026-03-2610$359K
BP2026-01255NewDaytona Homes2026-01-272026-02-026$335K
BP2026-00956NewDaytona Homes2026-01-212026-01-298$330K