How long does a Residential Improvement Project permit take in Vista Heights, Calgary?
Median days · Applied → Issued
41 days
Sample: 21 permits, last 24 months
Median days · Issued → Completed
50 days
From permit issuance to completion
City-wide median
17 days
Vista Heights is 24 days slower
Recent examples in Vista Heights
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14552 | New | — | 2026-08-03 | 2026-08-31 | 28 | $51K |
| BP2026-11082 | New | Hush Homes and Renovations | 2026-06-17 | 2026-08-14 | 58 | $112K |
| BP2026-10016 | Improvement | — | 2026-06-03 | 2026-06-18 | 15 | $5K |
| BP2026-02631 | New | Gk Groups | 2026-02-23 | 2026-06-08 | 105 | $39K |
| BP2026-02633 | New | Gk Groups | 2026-02-23 | 2026-06-08 | 105 | $39K |