How long does a Commercial / Multi Family Project permit take in University Of Calgary, Calgary?
Median days · Applied → Issued
3 days
Sample: 12 permits, last 24 months
Median days · Issued → Completed
6 days
From permit issuance to completion
City-wide median
42 days
University Of Calgary is 39 days faster
Recent examples in University Of Calgary
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13380 | Unspecified | — | 2026-07-17 | 2026-07-30 | 13 | $40K |
| BP2026-06455 | Unspecified | — | 2026-04-21 | 2026-04-24 | 3 | $8K |
| BP2026-01370 | Unspecified | — | 2026-01-29 | 2026-02-03 | 5 | $16K |
| BP2025-22157 | Unspecified | — | 2025-11-17 | 2025-11-18 | 1 | $3K |
| BP2025-20785 | New | — | 2025-10-23 | 2025-10-24 | 1 | $9K |