How long does a Commercial / Multi Family Project permit take in University District, Calgary?
Median days · Applied → Issued
45 days
Sample: 37 permits, last 24 months
Median days · Issued → Completed
170 days
From permit issuance to completion
City-wide median
42 days
University District is 3 days slower
Recent examples in University District
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15190 | Improvement | — | 2026-08-11 | 2026-08-28 | 17 | $150K |
| BP2026-11902 | Improvement | — | 2026-06-26 | 2026-08-04 | 39 | $150K |
| BP2026-09881 | Improvement | Delnor Construction | 2026-06-02 | 2026-07-21 | 49 | $248K |
| BP2026-05094 | New | Stealth Homes | 2026-04-01 | 2026-07-20 | 110 | $1.6M |
| BP2026-09662 | Improvement | — | 2026-05-30 | 2026-07-03 | 34 | $128K |