How long does a Commercial / Multi Family Project permit take in Temple, Calgary?
Median days · Applied → Issued
39 days
Sample: 10 permits, last 24 months
Median days · Issued → Completed
111 days
From permit issuance to completion
City-wide median
42 days
Temple is 3 days faster
Recent examples in Temple
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13586 | Improvement | — | 2026-07-21 | 2026-08-20 | 30 | $385K |
| BP2026-09980 | New | Kamex Construction | 2026-06-03 | 2026-08-18 | 76 | $75K |
| BP2025-15833 | Improvement | — | 2025-08-14 | 2025-09-23 | 40 | $100K |
| BP2025-06080 | Improvement | — | 2025-04-07 | 2025-05-02 | 25 | $0 |
| BP2025-00969 | Improvement | — | 2025-01-18 | 2025-02-28 | 41 | $125K |