How long does a Commercial / Multi Family Project permit take in Sunridge, Calgary?

Rolling 24 months · Sample: 104
Median days · Applied → Issued
44 days
Sample: 104 permits, last 24 months
Median days · Issued → Completed
121 days
From permit issuance to completion
City-wide median
42 days
Sunridge is 2 days slower

Recent examples in Sunridge

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13539Improvement2026-07-202026-09-1052$125K
BP2026-15877ImprovementKcp Energy2026-08-202026-09-0819$231K
BP2026-05260Improvement2026-04-052026-09-04152$40K
BP2026-05800Improvement2026-04-132026-08-27136$180K
BP2026-10953Improvement2026-06-152026-08-1965$10K