How long does a Residential Improvement Project permit take in Sundance, Calgary?
Median days · Applied → Issued
16 days
Sample: 96 permits, last 24 months
Median days · Issued → Completed
56 days
From permit issuance to completion
City-wide median
17 days
Sundance is 1 days faster
Recent examples in Sundance
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13087 | New | Sunurban Developments | 2026-07-14 | 2026-09-11 | 59 | $56K |
| BP2026-15511 | New | Smart Home Renovations Yyc | 2026-08-14 | 2026-09-10 | 27 | $35K |
| BP2026-16170 | Improvement | — | 2026-08-25 | 2026-09-10 | 16 | $47K |
| BP2026-15004 | Improvement | Roots Home Developments | 2026-08-09 | 2026-09-09 | 31 | $138K |
| BP2026-15899 | Improvement | — | 2026-08-20 | 2026-09-08 | 19 | $8K |