How long does a Residential Improvement Project permit take in Sundance, Calgary?

Rolling 24 months · Sample: 96
Median days · Applied → Issued
16 days
Sample: 96 permits, last 24 months
Median days · Issued → Completed
56 days
From permit issuance to completion
City-wide median
17 days
Sundance is 1 days faster

Recent examples in Sundance

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13087NewSunurban Developments2026-07-142026-09-1159$56K
BP2026-15511NewSmart Home Renovations Yyc2026-08-142026-09-1027$35K
BP2026-16170Improvement2026-08-252026-09-1016$47K
BP2026-15004ImprovementRoots Home Developments2026-08-092026-09-0931$138K
BP2026-15899Improvement2026-08-202026-09-0819$8K