How long does a Commercial / Multi Family Project permit take in Stoney 3, Calgary?

Rolling 24 months · Sample: 106
Median days · Applied → Issued
64 days
Sample: 106 permits, last 24 months
Median days · Issued → Completed
150 days
From permit issuance to completion
City-wide median
42 days
Stoney 3 is 22 days slower

Recent examples in Stoney 3

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14726Improvement2026-08-052026-09-0834$43K
BP2026-12328Improvement2026-07-022026-09-0464$15K
BP2026-12312Improvement2026-07-022026-08-3160$0
BP2026-09882Improvement2026-06-022026-08-2079$45K
BP2026-05848Improvement2026-04-132026-08-19128$70K