How long does a Commercial / Multi Family Project permit take in Stoney 3, Calgary?
Median days · Applied → Issued
64 days
Sample: 106 permits, last 24 months
Median days · Issued → Completed
150 days
From permit issuance to completion
City-wide median
42 days
Stoney 3 is 22 days slower
Recent examples in Stoney 3
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14726 | Improvement | — | 2026-08-05 | 2026-09-08 | 34 | $43K |
| BP2026-12328 | Improvement | — | 2026-07-02 | 2026-09-04 | 64 | $15K |
| BP2026-12312 | Improvement | — | 2026-07-02 | 2026-08-31 | 60 | $0 |
| BP2026-09882 | Improvement | — | 2026-06-02 | 2026-08-20 | 79 | $45K |
| BP2026-05848 | Improvement | — | 2026-04-13 | 2026-08-19 | 128 | $70K |