How long does a Commercial / Multi Family Project permit take in Stonegate Landing, Calgary?
Median days · Applied → Issued
36 days
Sample: 36 permits, last 24 months
Median days · Issued → Completed
75 days
From permit issuance to completion
City-wide median
42 days
Stonegate Landing is 6 days faster
Recent examples in Stonegate Landing
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15735 | Unspecified | Sprouse Fire and Safety | 2026-08-19 | 2026-08-21 | 2 | $6K |
| BP2026-03835 | Improvement | Nci Construction | 2026-03-12 | 2026-07-23 | 133 | $150K |
| BP2026-03544 | Improvement | Nci Construction | 2026-03-09 | 2026-07-16 | 129 | $550K |
| BP2026-05679 | Improvement | Leeswood Construction | 2026-04-10 | 2026-06-24 | 75 | $225K |
| BP2025-21940 | New | Scott Builders | 2025-11-12 | 2026-03-12 | 120 | $2M |