How long does a Commercial / Multi Family Project permit take in Stonegate Landing, Calgary?

Rolling 24 months · Sample: 36
Median days · Applied → Issued
36 days
Sample: 36 permits, last 24 months
Median days · Issued → Completed
75 days
From permit issuance to completion
City-wide median
42 days
Stonegate Landing is 6 days faster

Recent examples in Stonegate Landing

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15735UnspecifiedSprouse Fire and Safety2026-08-192026-08-212$6K
BP2026-03835ImprovementNci Construction2026-03-122026-07-23133$150K
BP2026-03544ImprovementNci Construction2026-03-092026-07-16129$550K
BP2026-05679ImprovementLeeswood Construction2026-04-102026-06-2475$225K
BP2025-21940NewScott Builders2025-11-122026-03-12120$2M