How long does a Commercial / Multi Family Project permit take in Starfield, Calgary?

Rolling 24 months · Sample: 39
Median days · Applied → Issued
36 days
Sample: 39 permits, last 24 months
Median days · Issued → Completed
99 days
From permit issuance to completion
City-wide median
42 days
Starfield is 6 days faster

Recent examples in Starfield

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15036ImprovementHopewell Development2026-08-102026-09-0829$214K
BP2026-06977New2026-04-282026-08-12106$7.3M
BP2026-09778ImprovementEngelhart Construction2026-06-012026-08-0565$750K
BP2026-07350NewLeeswood Construction2026-05-012026-07-2181$20.9M
BP2026-07349NewLeeswood Construction2026-05-012026-07-0868$21.7M