How long does a Commercial / Multi Family Project permit take in Starfield, Calgary?
Median days · Applied → Issued
36 days
Sample: 39 permits, last 24 months
Median days · Issued → Completed
99 days
From permit issuance to completion
City-wide median
42 days
Starfield is 6 days faster
Recent examples in Starfield
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15036 | Improvement | Hopewell Development | 2026-08-10 | 2026-09-08 | 29 | $214K |
| BP2026-06977 | New | — | 2026-04-28 | 2026-08-12 | 106 | $7.3M |
| BP2026-09778 | Improvement | Engelhart Construction | 2026-06-01 | 2026-08-05 | 65 | $750K |
| BP2026-07350 | New | Leeswood Construction | 2026-05-01 | 2026-07-21 | 81 | $20.9M |
| BP2026-07349 | New | Leeswood Construction | 2026-05-01 | 2026-07-08 | 68 | $21.7M |