How long does a Commercial / Multi Family Project permit take in South Foothills, Calgary?
Median days · Applied → Issued
70 days
Sample: 24 permits, last 24 months
Median days · Issued → Completed
44 days
From permit issuance to completion
City-wide median
42 days
South Foothills is 28 days slower
Recent examples in South Foothills
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11142 | Improvement | — | 2026-06-17 | 2026-09-02 | 77 | $10 |
| BP2026-10915 | Unspecified | — | 2026-06-15 | 2026-06-19 | 4 | $15K |
| BP2026-05434 | Unspecified | — | 2026-04-07 | 2026-05-06 | 29 | $145 |
| BP2025-23667 | Unspecified | — | 2025-12-14 | 2026-04-24 | 131 | $5K |
| BP2026-03015 | Improvement | — | 2026-02-27 | 2026-04-16 | 48 | $10K |