How long does a Residential Improvement Project permit take in Somerset, Calgary?
Median days · Applied → Issued
16 days
Sample: 65 permits, last 24 months
Median days · Issued → Completed
42 days
From permit issuance to completion
City-wide median
17 days
Somerset is 1 days faster
Recent examples in Somerset
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15831 | Improvement | Ridgecrest Developments | 2026-08-20 | 2026-09-04 | 15 | $5K |
| BP2026-15146 | Improvement | — | 2026-08-11 | 2026-09-02 | 22 | $0 |
| BP2026-14657 | Improvement | — | 2026-08-04 | 2026-08-26 | 22 | $19K |
| BP2026-13458 | Improvement | — | 2026-07-19 | 2026-08-24 | 36 | $8K |
| BP2026-14566 | New | — | 2026-08-03 | 2026-08-18 | 15 | $11K |