How long does a Commercial / Multi Family Project permit take in Skyline West, Calgary?
Median days · Applied → Issued
55 days
Sample: 14 permits, last 24 months
Median days · Issued → Completed
163 days
From permit issuance to completion
City-wide median
42 days
Skyline West is 13 days slower
Recent examples in Skyline West
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10072 | Improvement | — | 2026-06-03 | 2026-07-10 | 37 | $20K |
| BP2026-08804 | Improvement | — | 2026-05-20 | 2026-07-08 | 49 | $60K |
| BP2026-07904 | Improvement | — | 2026-05-08 | 2026-07-07 | 60 | $80K |
| BP2025-15075 | Improvement | — | 2025-08-04 | 2026-03-11 | 219 | $50K |
| BP2025-23647 | Improvement | — | 2025-12-12 | 2026-02-19 | 69 | $30K |