How long does a Commercial / Multi Family Project permit take in Skyline West, Calgary?

Rolling 24 months · Sample: 14
Median days · Applied → Issued
55 days
Sample: 14 permits, last 24 months
Median days · Issued → Completed
163 days
From permit issuance to completion
City-wide median
42 days
Skyline West is 13 days slower

Recent examples in Skyline West

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-10072Improvement2026-06-032026-07-1037$20K
BP2026-08804Improvement2026-05-202026-07-0849$60K
BP2026-07904Improvement2026-05-082026-07-0760$80K
BP2025-15075Improvement2025-08-042026-03-11219$50K
BP2025-23647Improvement2025-12-122026-02-1969$30K