How long does a Commercial / Multi Family Project permit take in Skyline East, Calgary?
Median days · Applied → Issued
44 days
Sample: 14 permits, last 24 months
Median days · Issued → Completed
77 days
From permit issuance to completion
City-wide median
42 days
Skyline East is 2 days slower
Recent examples in Skyline East
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12077 | Improvement | Trimax Construction | 2026-06-29 | 2026-09-08 | 71 | $100K |
| BP2026-11046 | Improvement | — | 2026-06-16 | 2026-09-04 | 80 | $0 |
| BP2026-14221 | Unspecified | — | 2026-07-28 | 2026-08-19 | 22 | $7K |
| BP2026-11262 | Improvement | — | 2026-06-18 | 2026-08-13 | 56 | $125K |
| BP2026-02479 | Improvement | — | 2026-02-18 | 2026-03-27 | 37 | $5K |