How long does a Commercial / Multi Family Project permit take in Sherwood, Calgary?
Median days · Applied → Issued
30 days
Sample: 22 permits, last 24 months
Median days · Issued → Completed
76 days
From permit issuance to completion
City-wide median
42 days
Sherwood is 12 days faster
Recent examples in Sherwood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14694 | Unspecified | — | 2026-08-05 | 2026-08-11 | 6 | $4K |
| BP2026-07789 | Improvement | Guru Ramdas Construction | 2026-05-07 | 2026-06-06 | 30 | $250K |
| BP2026-05167 | Unspecified | — | 2026-04-02 | 2026-04-09 | 7 | $4K |
| BP2026-00472 | Improvement | Trusted Developments | 2026-01-13 | 2026-02-11 | 29 | $500K |
| BP2026-01248 | Unspecified | — | 2026-01-27 | 2026-01-28 | 1 | $3K |