How long does a Commercial / Multi Family Project permit take in Sherwood, Calgary?

Rolling 24 months · Sample: 22
Median days · Applied → Issued
30 days
Sample: 22 permits, last 24 months
Median days · Issued → Completed
76 days
From permit issuance to completion
City-wide median
42 days
Sherwood is 12 days faster

Recent examples in Sherwood

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14694Unspecified2026-08-052026-08-116$4K
BP2026-07789ImprovementGuru Ramdas Construction2026-05-072026-06-0630$250K
BP2026-05167Unspecified2026-04-022026-04-097$4K
BP2026-00472ImprovementTrusted Developments2026-01-132026-02-1129$500K
BP2026-01248Unspecified2026-01-272026-01-281$3K

Other permit types in Sherwood