How long does a Commercial / Multi Family Project permit take in Shepard Industrial, Calgary?
Median days · Applied → Issued
49 days
Sample: 40 permits, last 24 months
Median days · Issued → Completed
110 days
From permit issuance to completion
City-wide median
42 days
Shepard Industrial is 7 days slower
Recent examples in Shepard Industrial
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15731 | Improvement | EllisDon Construction | 2026-08-19 | 2026-09-11 | 23 | $885K |
| BP2026-13307 | Improvement | Barjac | 2026-07-16 | 2026-08-10 | 25 | $100K |
| BP2026-10035 | Improvement | — | 2026-06-03 | 2026-07-20 | 47 | $1.3M |
| BP2026-06884 | Improvement | — | 2026-04-27 | 2026-07-17 | 81 | $35K |
| BP2026-06013 | Improvement | — | 2026-04-15 | 2026-05-22 | 37 | $120K |