How long does a Commercial / Multi Family Project permit take in Seton, Calgary?
Median days · Applied → Issued
41 days
Sample: 104 permits, last 24 months
Median days · Issued → Completed
168 days
From permit issuance to completion
City-wide median
42 days
Seton is 1 days faster
Recent examples in Seton
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14375 | New | — | 2026-07-30 | 2026-08-17 | 18 | $670K |
| BP2026-14718 | Improvement | EllisDon Construction | 2026-08-05 | 2026-08-13 | 8 | $178K |
| BP2026-13166 | Improvement | — | 2026-07-14 | 2026-08-13 | 30 | $125K |
| BP2026-03687 | Improvement | — | 2026-03-10 | 2026-08-11 | 154 | $35K |
| BP2026-11330 | Improvement | — | 2026-06-19 | 2026-07-27 | 38 | $1.8M |