How long does a Commercial / Multi Family Project permit take in Section 23, Calgary?
Median days · Applied → Issued
92 days
Sample: 17 permits, last 24 months
Median days · Issued → Completed
46 days
From permit issuance to completion
City-wide median
42 days
Section 23 is 50 days slower
Recent examples in Section 23
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2025-23554 | Improvement | — | 2025-12-11 | 2026-06-05 | 176 | $1K |
| BP2026-06666 | Unspecified | Sprouse Fire and Safety | 2026-04-23 | 2026-05-05 | 12 | $10K |
| BP2026-02550 | Improvement | — | 2026-02-20 | 2026-03-24 | 32 | $7K |
| BP2025-22419 | Improvement | — | 2025-11-20 | 2026-03-14 | 114 | $30K |
| BP2026-02874 | Unspecified | — | 2026-02-25 | 2026-02-27 | 2 | $3K |