How long does a Commercial / Multi Family Project permit take in Section 23, Calgary?

Rolling 24 months · Sample: 17
Median days · Applied → Issued
92 days
Sample: 17 permits, last 24 months
Median days · Issued → Completed
46 days
From permit issuance to completion
City-wide median
42 days
Section 23 is 50 days slower

Recent examples in Section 23

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2025-23554Improvement2025-12-112026-06-05176$1K
BP2026-06666UnspecifiedSprouse Fire and Safety2026-04-232026-05-0512$10K
BP2026-02550Improvement2026-02-202026-03-2432$7K
BP2025-22419Improvement2025-11-202026-03-14114$30K
BP2026-02874Unspecified2026-02-252026-02-272$3K