How long does a Commercial / Multi Family Project permit take in Sandstone Valley, Calgary?

Rolling 24 months · Sample: 3
Median days · Applied → Issued
94 days
Sample: 3 permits, last 24 months
Median days · Issued → Completed
22 days
From permit issuance to completion
City-wide median
42 days
Sandstone Valley is 52 days slower

Recent examples in Sandstone Valley

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-06382ImprovementRed Dot Restoration2026-04-202026-05-0414$26K
BP2025-14601Improvement2025-07-282025-10-3094$100K
BP2024-09964ImprovementKamex Construction2024-05-242024-09-19118$70K