How long does a Commercial / Multi Family Project permit take in Saddle Ridge Industrial, Calgary?

Rolling 24 months · Sample: 20
Median days · Applied → Issued
53 days
Sample: 20 permits, last 24 months
Median days · Issued → Completed
132 days
From permit issuance to completion
City-wide median
42 days
Saddle Ridge Industrial is 11 days slower

Recent examples in Saddle Ridge Industrial

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-11136Improvement2026-06-172026-07-1528$725K
BP2025-22337Improvement2025-11-192026-04-24156$200K
BP2025-21896Improvement2025-11-122026-03-27135$80K
BP2025-20867Improvement2025-10-242026-03-20147$549K
BP2025-21661Improvement2025-11-062025-12-1741$80K