How long does a Commercial / Multi Family Project permit take in Saddle Ridge Industrial, Calgary?
Median days · Applied → Issued
53 days
Sample: 20 permits, last 24 months
Median days · Issued → Completed
132 days
From permit issuance to completion
City-wide median
42 days
Saddle Ridge Industrial is 11 days slower
Recent examples in Saddle Ridge Industrial
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11136 | Improvement | — | 2026-06-17 | 2026-07-15 | 28 | $725K |
| BP2025-22337 | Improvement | — | 2025-11-19 | 2026-04-24 | 156 | $200K |
| BP2025-21896 | Improvement | — | 2025-11-12 | 2026-03-27 | 135 | $80K |
| BP2025-20867 | Improvement | — | 2025-10-24 | 2026-03-20 | 147 | $549K |
| BP2025-21661 | Improvement | — | 2025-11-06 | 2025-12-17 | 41 | $80K |