How long does a Commercial / Multi Family Project permit take in Royal Vista, Calgary?
Median days · Applied → Issued
34 days
Sample: 33 permits, last 24 months
Median days · Issued → Completed
104 days
From permit issuance to completion
City-wide median
42 days
Royal Vista is 8 days faster
Recent examples in Royal Vista
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13935 | Improvement | — | 2026-07-24 | 2026-08-27 | 34 | $230K |
| BP2026-13311 | Improvement | — | 2026-07-16 | 2026-08-18 | 33 | $100K |
| BP2026-12358 | Improvement | — | 2026-07-03 | 2026-08-12 | 40 | $15K |
| BP2026-12219 | Improvement | — | 2026-07-01 | 2026-08-07 | 37 | $150K |
| BP2026-14659 | Unspecified | — | 2026-08-04 | 2026-08-06 | 2 | $3K |