How long does a Commercial / Multi Family Project permit take in Royal Oak, Calgary?

Rolling 24 months · Sample: 8
Median days · Applied → Issued
24 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
273 days
From permit issuance to completion
City-wide median
42 days
Royal Oak is 18 days faster

Recent examples in Royal Oak

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13424ImprovementAbris Construction Calgary2026-07-172026-08-1327$789K
BP2026-12293ImprovementEarthworks 20012026-07-022026-07-2018$300K
BP2026-03789Improvement2026-03-122026-04-0120$1.3M
BP2025-18370Improvement2025-09-182025-11-0750$250K
BP2025-18544Improvement2025-09-222025-10-1321$25K