How long does a Commercial / Multi Family Project permit take in Royal Oak, Calgary?
Median days · Applied → Issued
24 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
273 days
From permit issuance to completion
City-wide median
42 days
Royal Oak is 18 days faster
Recent examples in Royal Oak
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13424 | Improvement | Abris Construction Calgary | 2026-07-17 | 2026-08-13 | 27 | $789K |
| BP2026-12293 | Improvement | Earthworks 2001 | 2026-07-02 | 2026-07-20 | 18 | $300K |
| BP2026-03789 | Improvement | — | 2026-03-12 | 2026-04-01 | 20 | $1.3M |
| BP2025-18370 | Improvement | — | 2025-09-18 | 2025-11-07 | 50 | $250K |
| BP2025-18544 | Improvement | — | 2025-09-22 | 2025-10-13 | 21 | $25K |