How long does a Single Construction Permit permit take in Rosedale, Calgary?

Rolling 24 months · Sample: 15
Median days · Applied → Issued
44 days
Sample: 15 permits, last 24 months
Median days · Issued → Completed
299 days
From permit issuance to completion
City-wide median
18 days
Rosedale is 26 days slower

Recent examples in Rosedale

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-09819NewCastle Stone Homes2026-06-012026-06-2524$688K
BP2026-06578NewVesta Ridge Custom Homes2026-04-222026-06-1756$662K
BP2026-04179NewCraftcore Homes2026-03-182026-06-1185$702K
BP2026-08524NewMission Homes Jv2026-05-152026-06-1127$934K
BP2026-06857NewRawlyk Developments2026-04-272026-05-1922$502K