How long does a Single Construction Permit permit take in Rosedale, Calgary?
Median days · Applied → Issued
44 days
Sample: 15 permits, last 24 months
Median days · Issued → Completed
299 days
From permit issuance to completion
City-wide median
18 days
Rosedale is 26 days slower
Recent examples in Rosedale
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-09819 | New | Castle Stone Homes | 2026-06-01 | 2026-06-25 | 24 | $688K |
| BP2026-06578 | New | Vesta Ridge Custom Homes | 2026-04-22 | 2026-06-17 | 56 | $662K |
| BP2026-04179 | New | Craftcore Homes | 2026-03-18 | 2026-06-11 | 85 | $702K |
| BP2026-08524 | New | Mission Homes Jv | 2026-05-15 | 2026-06-11 | 27 | $934K |
| BP2026-06857 | New | Rawlyk Developments | 2026-04-27 | 2026-05-19 | 22 | $502K |