How long does a Commercial / Multi Family Project permit take in Rocky Ridge, Calgary?
Median days · Applied → Issued
21 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
87 days
From permit issuance to completion
City-wide median
42 days
Rocky Ridge is 21 days faster
Recent examples in Rocky Ridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14441 | Unspecified | — | 2026-07-30 | 2026-08-05 | 6 | $4K |
| BP2026-07898 | Unspecified | — | 2026-05-08 | 2026-05-13 | 5 | $6K |
| BP2025-09933 | Improvement | — | 2025-05-27 | 2025-07-10 | 44 | $0 |
| BP2025-07990 | Improvement | Timber Valley Renovations | 2025-05-01 | 2025-06-02 | 32 | $400K |
| BP2025-08311 | Improvement | — | 2025-05-06 | 2025-05-27 | 21 | $5K |