How long does a Commercial / Multi Family Project permit take in Rideau Park, Calgary?

Rolling 24 months · Sample: 9
Median days · Applied → Issued
34 days
Sample: 9 permits, last 24 months
Median days · Issued → Completed
261 days
From permit issuance to completion
City-wide median
42 days
Rideau Park is 8 days faster

Recent examples in Rideau Park

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-03480ImprovementGoat Restoration2026-03-062026-04-0227$950K
BP2026-02850Improvement2026-02-252026-04-0135$80K
BP2025-11759ImprovementWelshboy Contracting2025-06-182025-08-0144$120K
BP2025-09909Improvement2025-05-272025-07-1549$225K
BP2025-05574Improvement2025-04-012025-05-2857$35K